Project context
A temporary steel load-introduction frame was designed to enable lifting of a large industrial asset using strand jacks. The permanent structure was not designed to accept direct lift loads, requiring a removable frame bolted to existing stiffeners.
Given the temporary nature of the works and the consequence of failure, the lifting contractor required independent confirmation that:
Load sharing would occur as intended
Local overstress would not occur at bolt groups and attachment plates
Second-order effects would not destabilise the system during lift synchronisation
Why FEA was essential
Hand calculations could demonstrate global strength but could not reliably assess:
Load redistribution due to differential jack stiffness
Local plate bending and bolt-group prying
Nonlinear contact behaviour at interfaces
Equitus FEA scope
Fully nonlinear 3D FEA including:
Contact interfaces between frame and permanent structure
Bolt preload and slip behaviour
Geometric nonlinearity to capture second-order effects
Parametric studies covering:
Jack stiffness variation
Minor out-of-plane misalignment
Partial loss of load in one lifting line
Outcome
Confirmed overall stability but identified unexpected local plate overstress
Enabled targeted stiffening without increasing frame mass
Provided Mammoet with a defensible engineering basis for execution sign-off
We endeavour to answer all enquiries within 24 hours on business days. We are happy to answer your questions.